An annual deadline, half a system

A phased approach kept a customer’s reporting intact when a full fix needed six more months.

The problem

Our largest customer runs one big survey a year, and the date doesn’t move. As it got closer, the new system was mostly ready but reporting wasn’t: the old reports had hard-coded metrics, and the new reporting depended on unfinished work. A full fix would have taken about six more months, and going without reporting wasn’t an option.

At a glance
~6 monthsthat a full fix would have needed
1phased plan agreed with leadership
0gaps in the customer’s reporting
What I did
  • I looked at the options and proposed a hybrid: survey setup and admin in the new system, reports staying on the old one for now.
  • I wrote down the risks, limitations and dependencies so the trade-off was clear.
  • The UK managing director had already accepted the approach. I briefed our CPO and explained the reasoning to our CTO, who came round fairly quickly.
  • I added the follow-up work to the backlog so the reporting move didn’t get forgotten.
What happened
  • The phased approach was agreed.
  • The customer kept its reporting through the survey.
  • The modernisation carried on without a stop.
What I’d do differently

I’d have been clearer with senior stakeholders, earlier, about what wasn’t going to make the deadline, and pushed harder to prioritise the functionality that worked around the reporting blocker.